Project Timeline Fiscal Year 2017-18 - Fiscal 2018-19

 

 

 

Project Description

Facility

Board Rank

Project Code

Cost Estimates

Vendor

March

April

May

June

July

August

Sept

 

New Tech Modifications

AHS

1

B

$250,000

TBD

Final Arch and Eng work complete with $ Estimates and bids received / approved.

Begin Construction

Construction

Finish Construction

 

 

More secure front entrance

MVES

2

S

$16,866

Construction TBD & First Witness Security

Quote Request Submitted and Received

Construction

 

 

 

 

More secure front entrance

AHS

3

S

$13,671

Construction TBD & First Witness Security

Quote Request Submitted and Received

Construction

 

 

 

 

More secure front entrance

CMS

4

S

$16,866

Construction TBD & First Witness Security

Quote Request Submitted and Received

Construction

 

 

 

 

More secure front entrance

SES

5

S

$23,921

Construction TBD & First Witness Security

Quote Request Submitted and Received

Construction

 

 

 

 

Replace EPDM roof sections 2,4 & 5 of  Sharon school - Phase 2 of 3

SES

9

B

$199,500

TBD

Project Presented

RFP Request Submitted / Received

Construction

Finish Construction

 

 

Replacement of ballasted roof over boy's locker room

AHS

10

B

$45,000

TBD

Project Presented

RFP Request Submitted / Received

Construction

Finish Construction

 

 

 

*Fiscal Year 2017-18

*Fiscal Year 2018-19